Penn Medicine Tuttleman Center

4th Floor Pre Op/2nd Stage Recovery (Occupied Renovation. ICRA level 3), 4th Floor Waiting Area (Occupied Renovation. ICRA Level 3), 5th Floor OR 1 &2 (Occupied Renovation. ICRA Level 4).

Construct ICRA compliant partitions, and negative air.

Removal of all existing millwork, flooring, wall finishes, ceiling tiles, lighting, plumbing fixtures

Installation of all new flooring, millwork, LED light fixtures, plumbing fixtures.

Construct ICRA compliant partitions, and negative air.

Removal of all existing millwork, flooring and wall finishes

1000 sf renovation of 2 existing OR’s on an occupied sterile Operating Room Floor

Construct ICRA compliant partitions, and negative air.

Removal of all ceilings, millwork, flooring, wall finishes, equipment, electrical, plumbing, HVAC, Med Gas, sprinkler

Provide all new electrical feeds to new Isolation panels, new electrical wiring throughout.

 